Ranked 38th amongst the ‘India Fastest Growing Mid-Size Enterprises’ by ‘The Magazine INS India 500’ in the survey of more than 5000 companies
Ranked 8th in the Sector-Wise Construction Sector ranking
Fabrication and erection work of Jawaharlal Nehru Stadium, Delhi- largest sports stadium in the country
Fabrication & Erection of Longest Steel Truss of 107m span, weighing 250MT, for Thyagraja Netball Stadium of Commonwealth Games
Erection of inclined, three dimensional steel columns- inclined at 72o– of 44m length and weighing 150MT for Jawaharlal Nehru Stadium for Commonwealth Games; erected using four crawler cranes in tandem
Longest arch Foot Over Bridge at New Delhi
Construction of longest span of 125m of cantilever erection for Rail cum Road Bridge at Munger, Bihar
First of its type Steel Tub Girders of 44m span for Mukarba Chowk Grade Separator at Delhi
Fabrication and erection of 110 m span Open Web Girder Bridge, weighing 850 MT, across Bhakra Main Line Canal on National Highway between Kharar and Kiratpur Saheb in Punjab; erected by Cantilever Push Launching
Commissioning of 3 x 2.5 MW Brenwar Small Hydro Electric Project commissioned in Village Brenwar, District Budgam, Jammu and Kashmir; the first HEP of the state
Commissioning of 2.0 MW Gogripur Small Hydro Power Project in Karnal, Haryana; it was the first Canal Based IPP in Haryana
Longest penstock of 3 km at Brenwar (J&K) in the sub 10MW category
Erection of Penstock Liner- inclined at 52o– in a longest underground inclined shaft of 600m length for 192 MW ADHPL Hydroelectric Power Project in Himachal Pradesh
Erection of 4.7m diameter penstock steel liner in 3 No. Vertical Shafts of 180m depth for Teesta Stage V Hydro Power Project of NHPC Ltd. in Sikkim
Fabrication and Erection of Penstocks of 7 m diameter for Teesta Low Dam III Hydro Power Project, NHPC Ltd. in West Bengal
2 MW of continuous dewatering for a period of 2 years at Mukerian Hydel Power Project, Punjab, for Punjab State Electricity Board
Steel flues for highest chimney of India (279 m) at NTPC Thermal Power Plant, Talcher, Odisha
Fabrication and Erection of main columns of Turbo Generator Building of NTPC Talcher Expansion Project in a single piece of 40 m length and up to 50 MT weight
Longest Steel I-girder of 55m span, weighing 70MT, for ROB at Pathankot, Punjab
Fabrication of 1400 MT of Structural Steel works in a single month in a single contract
Erection of 2000MT of a structural work in a single month for a single contract